The main hall had a parquet floor for dancing and in the forward section
was the toilet facilities, kitchen and snooker room. The main hall was
also used for whist drives and later bingo sessions.
The commissioners owned the land to the side and rear of the hall and
in 1959 they erected a garage for their tractor in that location. This
was later doubled in width as storage for more equipment was needed. The
triangular grass plot to the rear then became an open depot when the
last of the private bungalows in the park was built and the area was
effectively fenced off.
Eventually Pennington Hall was purchased by the commissioners and became
the main depot for the Parks Department. The Marion Road Garage
was subsequently demolished to make way for the Marion Court development
of local authority housing.
Work started on the demolition of Pennington Hall on Thursday 19th July. The
building is to be replaced by a steel framed structure which will embody
the tractor garage into the main complex with mechanical workshop, staff
facilities and storage. A lean-to shelter at the rear will house
the motor boats in the winter months.
The demolition by J.C.K. only took a couple of days to complete
and now
the site awaits the start of construction by contractors Parkinson.
In
the background are the rear of properties in Alberta Drive and beyond
are the red roofs of houses in Royal Avenue. On the skyline behind
them
is the top of the spire of St Peter's Church. |
Following demolition of Pennington Hall part of the Parks Department
depot is revealed. The greenhouse is used to bring on plants in the
springtime. The tree in the centre of the site is a specimen tree
which
is to remain and will not be affected by the building works. |
This photograph shows the foundation trenches dug for part of the
new
Pennington Hall depot. In the background are private bungalows which
face onto The Park. |
Another view of the site shows the commissioners' greenhouse which
is
now on a higher level due to overall excavation of the site. Concrete
bays are being laid in the background to form a working platform.
New
fencing has been erected to the north and east of the site. |
By mid September the block work had been built up from the deep
set
foundations and brought up to finished floor level. In the foreground
to
the right is a plastic hose used in pumping out the excavations prior
to
concrete and block work. In the background can be seen the shuttering
work running across the site into which concrete will be poured to
form a
low wall. This will be part of a lean to building in which the motorboats
will be kept during the winter period. |
By
the beginning of October the base to the new boat shelter was cast
in concrete as can be seen in the foreground with the holding down
bolts for the steel frame showing above the surface.
The boat shelter was
originally to be a lean-to at the rear of the main building to
take
advantage of the rear wall and shelter from the prevailing wind
but a
decision was taken to construct it as a stand alone building. |
The main building is also awaiting the arrival of a steel frame
and
pockets have been left in the block work for the uprights to be lowered
into. This view is taken from within the site and is looking towards
Marion Court, the commissioners' housing complex built at the top
of
Marion Road and behind The Park bungalows.
Behind the hoarding can
be
seen a large plastic tank which is known as an interceptor. It
will sit
beneath the surface of the new concrete yard with all the rainwater
drains passing through it. The object is to collect any solid
matter
washed off vehicles so that it doesn't make its way through the
storm
water drains which end up as the stream through Port Jack Glen. |
On Monday 8th October a crane moved onto the site to erect the
steel
framework. The picture shows the framework being erected for the
boat
store behind the main building. The work is being carried out by
steel
fabricators Wilson and Collins of Balthane.
Both Percy Wilson and
Des
Collins originally worked at Gellings Foundry on South Quay and
when they set up in business in the mid 60s, they started the business
in
Onchan at Tromode in a building belonging to Clucas' Laundry.
|
Work
has continued with the erection of steelwork on the main building
at the front. This will have staff facilities at one end and
a workshop at the other. The space in-between will house the
tractors, grass cutters and other equipment. The peak on the
front of the building is a decorative feature in the form of a gablet
to break up the elevation. There will be mezzanine storage
above the staff accommodation and workshop but the rest of the
building is single storey.
|
FEBRUARY 2008
The main building takes shape with the finishing touches being
put to the roof. The ventilator on the roof is purely for
decoration. The walls are partly finished in buff coloured
facing brick and the remainder in white spar dash to match the
domestic properties in the area. |
MARCH 2008
By the end of the month the hoardings were down and work started
in front of the building on paving and the creation of a parking
lay-by. This elevation faces the side of Marion Court and
the top of Marion Road. In the distance a ready mix concrete
lorry discharges its load as the driveway into the rear courtyard
is created. |
A view taken from the other end of the front elevation showing
the feature panels in the centre section to simulate garage door
openings but these are all located at the rear of the building taking
access from the courtyard. Also showing on the front elevation
either side of the double windows are the white plastic expansion
strips which are used in modern day construction to avoid cracking. In
pre-war building lime mortar was used to allow for movement in the
structure without cracking. |
In the yard a free standing boat shelter has been erected
to accommodate the motorboats from the lake during the winter months. This
was originally intended to be a lean-to stricture on the rear of
the main building from which it would derive shelter from the prevailing
winds. This steel framed structure has been finished with a
tiled roof to match the main building and the gables are tile hung. The
contract does not include any form of cladding to the walls. |
View
of the rear of the main building showing the courtyard that is
being created between it and the boat shelter. The roof
lights on the main building are not to an upper floor but to the
interior of the building which extends up to the apex of the roof. The
maximum height of vehicle which can enter the building is governed
by the vertical rolling doors on the rear elevation. On the
right the two windows are to the toilet and wash facilities for
the parks staff.
The two roller doors are the access for the tractors and other vehicles. The
double doors to the left of the picture give access to the compressor
which produces compressed air for the workshop whilst the single
door next to it is the fuel store. |
A view inside the building showing the full height building with
rear roof lights and overhead industrial lighting. At the end
of the building is the access to the staff mess facilities above
which lightweight storage can take place. The high open space
section is intended for the overnight parking of tractors, sit-on
mowers and the pick-up trucks used by the parks staff. |
A view inside the mechanic's workshop shows some of the benching
around the room. The workshop is at the opposite end of the
building to the mess facilities and is near to Royal Avenue. The
fencing visible through the rear windows has been erected as
a boundary between the rear yard and the properties in Alberta
Drive backing onto the compound. |